During December 2025, we carried out work to a Warehouse roof in burgess Hill, West Sussex.
The roof was leaking in numerous areas where the sheets had delaminated. This was due to the moss on the roof. In a couple of areas the leaks were so bad it had caused the plasterboard liner panels to fall.
We therefore cleaned down the moss that was growing on the sheets and the end laps which was preventing water draining down the roof effectively.
The moss from the roof and the waste from the gutters was then lowered to ground level.
We fitted 14 no. new overlay sheets to cover over the damaged sheets. This cured the existing leaks as well as helped prevent further leaks.
All of the new sheets were secured using new fixings.
2 no. new plasterboard liner panels were also fitted.